From 1 January 2027, a new electricity tariff structure will come into effect for customers connected to high-voltage (HV) and extra-high-voltage (EHV) networks. The changes will primarily affect industrial companies, manufacturing facilities, hospitals, universities and other organisations with extensive energy operations. For some customers, the new system may lead to higher regulated charges, while for others it could create opportunities to reduce costs.
The Energy Regulatory Office (ERÚ) does not intend to increase the overall volume of regulated charges, but rather to distribute costs more accurately according to the actual demands individual customers place on the electricity grid. According to ERÚ estimates, the changes could help release up to 3,300 MW of long-term unused reserved connection capacity, representing approximately 15% of the existing distribution network capacity at these voltage levels.
New Charges to Better Reflect Distribution Network Usage
The existing charges for reserved capacity and exceeding that capacity will be replaced by two new components: a charge for reserved connection capacity specified in the connection agreement and a charge for maximum power demand, calculated based on the highest average power demand recorded during any 15-minute interval in the relevant month. The new system introduces two tariff options (T1 and T2), with the more financially advantageous option automatically applied to each customer.
The changes may have a particularly significant impact on organisations whose reserved connection capacity has long exceeded their actual operational needs. A typical example is a manufacturing facility where production has been reduced, technologies have been modernised or energy consumption has decreased, without corresponding adjustments to the contractual connection parameters. At the same time, managing peak power demand will become increasingly important, as demand peaks may affect monthly distribution charges.
Unused Reserved Capacity May Lead to Higher Costs
The starting point for assessing potential savings is to compare the contracted reserved connection capacity with actual electricity demand patterns. Analysing historical 15-minute interval data makes it possible to identify unused capacity, recurring demand peaks and opportunities to adjust operating schedules.
However, a difference between reserved connection capacity and actual peak demand does not automatically mean that reducing the contracted capacity is advisable. Seasonal fluctuations, exceptional operating conditions and planned investments must also be considered, including the electrification of heating, expansion of production or development of electric vehicle charging infrastructure. Furthermore, capacity that has been released may not be available again under the same conditions in the future.
In addition to adjusting contractual parameters, managing peak demand, optimising the simultaneous operation of energy-intensive technologies and making effective use of on-site electricity generation and energy storage can also deliver economic benefits. However, the specific benefits of these measures will vary depending on the nature of the operation and its electricity demand profile.
Effective Optimisation Requires Reliable Data and Long-Term Planning
The new tariff structure highlights the growing importance of interval metering and systematic energy management. The economics of operations will no longer depend solely on the amount of electricity consumed, but increasingly on the required connection capacity and how that capacity is utilised over time.
Preparations for changes to the tariff structure at the low-voltage level are moving in a similar direction, with pilot projects expected to begin in 2028 and broader implementation on a voluntary basis anticipated from 2030.
For HV and EHV customers, however, the key milestone is already the beginning of 2027. A timely assessment of contractual parameters, actual electricity demand patterns and future energy requirements can help prevent unnecessary cost increases. The objective is not to minimise reserved connection capacity at all costs, but to ensure that it reflects both current and future operational needs.